Current position: Home>English>Life>Transportation
Latest news from Shenyang Metro
Source: Shenyang WeChat Official Account 2023-10-11

Have you taken metros in Shenyang during the past holiday?Have you felt the popularity of metros in Shenyang?

During the Mid-Autumn Festival and National Day holiday,the Shenyang Metro network recorded 13.0254 million passenger trips,daily passenger trips averaged 1.6282 million,the operation mileage was 510,400 kilometers,metro trips reached 16,500,and the maximum daily passenger trips reached 1.72 million.

On September 29,double lines of Shenyang Metro started operation,connecting "three railway stations and one airport" and opening a new chapter in "air-rail combined transportation".Have you experienced them?

Good news!Here comes the latest progress on the East Extension Line of Shenyang Metro Line 1!The main structure of the Zhiwuyuan Station has been completed and the construction of the auxiliary structure inside the station is underway.

The East Extension Line Project of Shenyang Metro Line 1 is the east extension of the existing Line 1. The project starts from the section behind the existing Limingguangchang Station of Line 1 in the west and ends at Shuangma Station in the east. It will connect Dadong District, Hunnan District, Qipan Mountain Scenic Area and the main urban area, and effectively drive the development of the eastern part of the city after completion.

The main lines of the East Extension Line of Shenyang Metro Line 1 are approximately 16.1 kilometers long in total, all of which are underground lines. There are a total of 10 stations, as well as the Mantang Parking Lot.

The 10 stations of the East Extension Line of Metro Line 1 are named as follows: Xinhuijie Station, Xinningjie Station,Dongdayingjie Station, Nongyedaxue Station, Qianling Station, Donglinggongyuan Station, Shuiquan Station, Boguanbeidajie Station, Zhiwuyuan Station and Shuangma Station.

As of the end of September 2023,the main structures of 10 stations on the East Extension Line of Shenyang Metro Line 1 have been completed.

At present,the construction of sections and station auxiliary structures is underway,and each station is undergoing professional constructions including the masonry and the installation of ventilation,water and electricity.

Looking forward to its completion!