How's the construction of the metro line near your home going?Here are the latest progresses of the five metro lines under construction in Shenyang!
The first phase of Line 6
The main structure of the stations has been completed by 76%,and nearly half of the sections have been constructed.
As of now, the construction of the first phase of Line 6 is progressing smoothly. The construction of the main structure of 29 stations has been completed by 76%, and the construction of main structure of 30 sections has been completed by 43%. Workers are making every effort to advance the construction of the main structure of the remaining stations and sections.
The East Extension Line of Line 1
The joint commissioning of the station equipment systems has been completed.
By mid-to-late May, the train debugging of the East Extension Line of Line 1 has been completed by 71%, and the dynamic acceptance of all 27 trains on the main line has been fully accomplished.
The joint commissioning with the equipment systems (communication, signal, platform door, AFC and FAS) has been completed. The point-to-point debugging with the controlled equipment of ventilation, water and electricity has been completed by 3%, with an accumulated completion rate of 85%. The accumulated completion rate of the system joint commissioning is 65%.
The second phase of Line 10
The excavation for the main body of the stations has already begun.
As of now, among the 19 construction sites along the entire line, 13 sites have completed the retaining pile construction, and 5 sites are currently advancing with the retaining pile construction. The overall completion rate has reached 93%.
By the end of May, all the retaining piles are expected to be completed. Among the 14 stations (excluding Shenyangnanzhan Station), the earthwork excavation for three stations including Mozishangongyuan Station is about to start, and the earthwork excavation for six stations including Chuangxinyilu Station is in full swing.
The eastern section of the first phase of Line 3
The construction of the main structure of the stations and the sections is nearly completed.
In May, the track project of the eastern section of Line 3 totaled 27,742 single linear meters, of which 11,500 single linear meters have been completed, accounting for 41%. The main structure construction of 12 stations and 12 sections has been completed, accounting for 92% and 86% respectively.
The second phase of Line 9
The main structure construction of 5 stations has been completed by 40%.
At present, the concrete pouring for the ninth section mezzanine floor is ready to proceed, and the shield machine for the right line of the section between Chang'anqiaonanjie Station and Xinlipuqiao Station has completed its entry. It is expected that the assembly of the shield machine will be completed by the end of the month.
As of mid May, the main structure construction of 5 stations has been completed by 40%, and the main structure construction of 6 sections has been completed by 16%.
Looking forward to the completion and opening of these lines!