The latest progress of Shenyang Metro Line 3
Source: Shenyang WeChat Official Account 2024-08-16

Here comes the latest progress of Shenyang Metro Line 3!

On August 14,the power supply for the dynamic lighting system of the third bid section of ventilation, water and electricity of Shenyang Metro Line 3 was successfully accomplished,marking that the first phase project of Shenyang Metro Line 3 entered the crucial segments such as single commissioning and joint commissioning,and took a crucial step towards the goal of being completed and opened to traffic.

The first phase project of Shenyang Metro Line 3 starts from BMW plant in Tiexi District in the west and ends at Xintai Street.

The third bid section project involves 5 stations, namely Qiandaohujie Station, Nanyanghujie Station, Datonghujie Station, Yuhongxincheng Station and Fangxingguangchang Station, 5 sections and 1 parking lot.

The primary construction scope encompasses the power lighting system, the ventilation, air conditioning and heating system, the water supply & drainage and water fire protection system, the secondary masonry, and the decoration engineering.

It took 9 days for the power transmission of the western part project to be accomplished.

On August 5, the western part project of Shenyang Metro Line 3 successfully accomplished the node goal of power supply in place, and the power lighting equipment system officially began the power receiving and commissioning stage.

The Shenyang Metro Project Department seized the "golden period" of construction and accomplished the power transmission work for the power lighting equipment specialty in just 9 days ahead of schedule, providing power guarantee for the equipment debugging of communication, signal, FAS, BAS and other specialties.

The Shenyang Metro Line 3 is a key east-west line in the southern part of the urban central area.Once completed,it will further enhance the urban rail transit network and make travel more convenient!

Looking forward to it!