The project construction is in peak period
Source: Shenyang WeChat Official Account 2022-12-13

Recently, the Zone C and the refrigeration station medium pressure chamber of the paint shop re-expansion project of the product upgrading project (Dadong Plant Area) of BMW Brilliance Automotive Co., Ltd., in whose construction the Northeastern Branch Company of China Construction Industrial & Energy Engineering Group Co., Ltd. participated, were officially handed over.

The subsequent installation of process air ducts, fire annihilator pipes and equipment will be carried out.

It marks the project construction has entered the peak period.

The total construction area of the paint shop is 25,000 square meters.

The Northeastern Branch Company of China Construction Industrial & Energy Engineering Group Co., Ltd. is responsible for the mechanical and electrical installation of the project.

Up to now, 71% of the mechanical and electrical installation has been completed.

Next, the project team and the construction team will work together to complete the follow-up work in the Zone C. Meanwhile, they will also carry out the construction of cable trays, smoke exhaust pipes, power pipes and fire annihilator pipes in the Zone D, the refrigeration station machine room and the dangerous goods warehouse area of the paint shop.

It is reported that the product upgrading project of BMW Brilliance Automotive Co., Ltd. is expected to be put into use by the end of 2023.

The project will jointly produce with BMW Brilliance Plant Lydia, helping Shenyang become the largest production base of BMW Group in the world.