The construction in Shenyang does not stop in winter
Source: Shenyang-China 2023-12-04

As of now, 58% of the bridge substructure and 10% of the upper structure have been completed for the Yuanjiang Street Expressway Project; Yuanjiang Street Third Ring Interchange Project has completed 365,000 cubic meters of roadbed filling, accounting for 74.0%, and its bridge project has completed 2,492 linear meters, accounting for 79.2%.